Thursday, June 16, 2016

Empennage

Aft Fuselage ( 3 hrs)

Sect 10-14;  routed Aft Fuselage Harness & Phone Cable along F01486A-L J-Stiffener. Challenging to insure correct cable leads are routed appropriately, per diagrams in 10-25 and 10-26.  



Need helper to position RH Skin onto assembly, so worked ahead on 10-15 Aft Bottom Skin:  Used band-saw to remove extra material both sides, "sanding" flush to line with belt sander.   Then deburred all edges & holes, drilled larger diameter holes, and finally dimpled #40 holes. Ready to prime and rivet next.
Trimmed pieces (scrap).   Cleco'd rearmost bulkhead as test fit...A-OK.