Canopy frame assembly  ( 3 hrs )

Today I ordered the bundled Lycoming IO-390 (w/ E-Mag option) plus the Hartzell 74" Blended Airfoil propellor via Van's ...just ahead of the Sept 1 deadline to gain the $1000 discount.    In the shop, continued Sect 38-09 Steps 1-5.  Required using both rivet gun/bucking bar and the "Main Squeeze" to get these rivets done - and one joint required blind rivets.   Ready to add Splice plates joining LH to RH frames.
 

holding during riveting is critical.

ready to add center Splice plates joining LH to RH frames