Thursday, June 15, 2017
Fuselage
›
Masking for Interior Paint ( 2 hrs ) Great help from Nancy today masking forward areas, including hard to reach firewall area. Decided to ...
Wednesday, June 14, 2017
Fuselage
›
Prep for Interior Painting ( 5 hrs ) Installed Idler Arms per Sect 36=02 Step 2 - torqued AN4 bolts. Sure moves easily. Riveted Bellcra...
Tuesday, June 13, 2017
Fuselage
›
Aileron & Elevator Systems ( 3 hrs ) While I'm pending final decision on interior paint (and procrastinating a bunch of masking), ...
Monday, June 12, 2017
Fuselage
›
Flap Torque Arms ( 3 hrs ) Installed LH & RH Flap Torque Arms. First sanded bearing surface transition to powder coated paint on tube...
Saturday, June 10, 2017
Fuselage
›
Interior color & Flap Actuation Ass'ly ( 3 hrs ) Getting ready to paint interior color, so I've examined other builders experi...
Friday, June 9, 2017
Fuselage
›
Baggage Side Panels ( 3 hrs ) Completed RH Baggage Side Panel riveting - so both sides done. Yay ! Looks great. While still exploring w...
Wednesday, June 7, 2017
Fuselage
›
Baggage Side Covers ( 3 hrs ) Deburred edges and holes, dimpled as needed Baggage Side Covers. After priming, riveted LH side panels to...
‹
›