Steevo's RV14a Build Log
Wednesday, January 17, 2018
Firewall Forward Kit
›
Stein Air non-Panel components (1 hr) Rec'd large package from Stein Air including all components that aren't directly mounted on ...
Tuesday, January 16, 2018
Finish Kit
›
Wing Root Fairings ( 4 hrs ) Completed LH & RH Wing Root Fairings per Sect 41-04, Steps 1-14 (except Steps 6-9 requiring Wings install...
Monday, January 15, 2018
Finish Kit
›
Torq Seal and Wing Fairings ( 2 hrs ) Did some "clean up" of some loose ends in Fuselage: climbed into Fuse and managed to twis...
Saturday, January 13, 2018
Firewall Forward Kit
›
Sender Mount, etc ( 3 hrs ) Installed Sender Mount, adding fittings and hoses VA-102 and VA-119 (from Sect 49-11, Fig 2) prior to bolting ...
Friday, January 12, 2018
Firewall Forward
›
Starter Solenoid and Master Relay ( 3 hrs ) Started FF Kit ahead of engine delivery -- so I could mount components to Firewall easily. In...
Wednesday, January 10, 2018
Firewall Forward Kit
›
Prep for FF Kit / some Pushrods from Finish Kit ( 2 hrs ) Minimal shop time Jan 8 - 10 while working phones and emails with Vans, Stein Ai...
Saturday, January 6, 2018
Firewall Forward Kit
›
Firewall Forward Kit Inventory ( 9 hrs ) Rec'd FF Kit on Jan 4 via Fed Ex in 3 medium size boxes. One weighed 60 lbs, but other 2 wer...
‹
›
Home