Steevo's RV14a Build Log
Friday, October 12, 2018
Avionics
›
Radio Installation ( 3 hrs ) Just returned from 2 wk "road trip" to Niagara Falls, Montreal, and Quebec City in Canada and Bar H...
Friday, September 21, 2018
Avionics
›
Misc installations at IP ( 3 hrs ) Installed 8-32 screw & locknut anchoring Glove Box to Subpanel. Installed CO Detector Test/Reset ...
Wednesday, September 19, 2018
Avionics
›
Instrument Panel installed ( 4 hrs ) Big day ! With excellent help from Rex (brother-in-law) and wife, Nancy we lifted IP into cockpit. ...
Tuesday, September 18, 2018
Avionics
›
Install GPS 20A, etc ( 3 hrs ) Installed 4 nutplates and mounted GPS 20A. Removed canopy. Prepped for installing Instrument Panel next. ...
Monday, September 17, 2018
Avionics
›
GAD27 and GPS20A installed ( 3 hrs ) Measured GAD27 (already connected to IP harness by Stein Air, so didn't remove) to make a templat...
Saturday, September 15, 2018
Avionics
›
GEA 24 and Avionics Bus install ( 2 hrs ) Installed four 10-32 nutplates to sub-panel, then mounted Garmin GEA 24. Made cardboard tem...
Thursday, September 13, 2018
Avionics
›
Installing GEA24 on sub-panel ( 2 hrs ) Drilled four #10 holes for mounting Garmin GEA24 on sub-panel. Drilled #40 holes for nutplates fo...
‹
›