Thursday, October 18, 2018

Avionics

›
Main Harness supports ( 1 hr ) Installed both brackets for large snap bushings supporting main harness passing through Vertical Supports. ...
Wednesday, October 17, 2018

Avionics

›
Instrument Panel main harness ( 3 hrs ) Per discussion with Josh at Stein Air, determined "Discrete 2" wire best re-routed to ...
Monday, October 15, 2018

Avionics

›
Instrument Panel wire protection ( 2 hrs ) Added wire protection at various locations, including edge protection and either split corrugat...
Friday, October 12, 2018

Avionics

›
Radio Installation ( 3 hrs ) Just returned from 2 wk "road trip" to Niagara Falls, Montreal, and Quebec City in Canada and Bar H...
Friday, September 21, 2018

Avionics

›
Misc installations at IP  ( 3 hrs ) Installed 8-32 screw & locknut anchoring Glove Box to Subpanel.  Installed CO Detector Test/Reset ...
Wednesday, September 19, 2018

Avionics

›
Instrument Panel installed ( 4 hrs ) Big day !   With excellent help from Rex (brother-in-law) and wife, Nancy we lifted IP into cockpit. ...
Tuesday, September 18, 2018

Avionics

›
Install GPS 20A, etc ( 3 hrs ) Installed 4 nutplates and mounted GPS 20A.  Removed canopy.  Prepped for installing Instrument Panel next. ...
‹
›
Home
View web version

About Me

My photo
Steevo
Wickenburg, Arizona, United States
I'm building an RV-14A kit airplane purchased from Van's Aircraft. This website documents construction to show I've built in accordance with FAA's 51% rule. When finished it will be inspected by the FAA or designated representatives, and a special airworthiness certificate will be issued under the Experimental category.