Steevo's RV14a Build Log
Saturday, June 29, 2019
Finish Kit (and others for Final Assembly)
›
Prep & First Engine Run ( 6 hrs ) Friends and RV builders Terry Moushon (RV10) and Bill Lane (RV7) were terrific help preparing my IO-...
Friday, June 28, 2019
Finish Kit (and others for Final assembly)
›
Pitot/Static and Transponder certification ( 3 hrs) Byerly Aviation of Peoria, Illinois (Brandon and Drake) performed Pitot/Static certifi...
Thursday, June 27, 2019
Finish Kit (and others for Final Assembly)
›
Magnetometer Interference and Joystick re-position ( 5 hrs ) Repeated full Magnetometer Interference test. Again, Pitot Heat wa...
Wednesday, June 26, 2019
Finish Kit (and others for Final Assembly)
›
ADAHARS and Magnetometer Calibrations ( 7 hrs ) Performed ADAHARS (Garmin installation manual 35.4.7) and Magnetometer GMU 22 Calibrations...
Tuesday, June 25, 2019
Finish Kit (and other categories for Final Assembly)
›
Fuel Flow test for Pitch Up attitude ( 4 hrs ) Completed RH Tank calibration of fuel levels - see June 24 entry. Then I raised nose unti...
Monday, June 24, 2019
Finish Kit (and others for Final Assembly)
›
Flow test from LH Fuel Tank, Calibrate Fuel Senders ( 4 hrs ) Continued testing Fuel Flow rates for LH Tank, repeating process used for RH...
Saturday, June 22, 2019
Finish Kit (and others...for Final Assembly)
›
Fuel Flow testing ( 3 hrs ) Set up to test fuel flow rates with Aux Boost Pump, including determining Unusable Fuel in tank, and to flush ...
‹
›