Steevo's RV14a Build Log
Wednesday, April 13, 2016
Empennage
›
Elevator ( 4 hrs ) Completed Step 7 for RH top and bottom Skins and Step 8, Countersink TE Wedges. These countersinks required a few cl...
Tuesday, April 12, 2016
Empennage
›
Elevator ( 3 hrs ) Step 5 at Sect 9-09: Dimple #40 holes (3/32") on Counterbalance Skins. Requires using Modified male Dimple di...
Sunday, April 10, 2016
Empennage
›
Elevator (2 hrs ) Con'td Sect 9-09 Step 4: More deburring all holes and edges of Tip Rib Assembly (6 parts) and 4th of 4 Skins. ...
Friday, April 8, 2016
Empennage
›
Elevators ( 5 hrs ) Continued Sect 9-09 at Step 3. Finished Final Drill #40 and #30 for all holes on RH Elevator. Then marked parts and...
Thursday, April 7, 2016
Empennage
›
Elevators ( 2 hrs ) Sect 9-09, Setp 2 Attached (cleco'd) LH and RH Elevator Horns. #30 (ie 1/8" holes) drilled at twelve times ...
Empennage
›
Elevator ( 2.5 hrs ) April 6 , 2016 Cont'd Sect 9-08, Steps 2 & 3: Cleco'd RH and LH Tip Assly's to Bottom Skins and...
Tuesday, April 5, 2016
Empennage
›
Elevator (0.5 hrs) Cont'd Sect 9-07: Completed Steps 4-6 for Trim Tab Hinges - Drilled #40 holes, and trimmed ends flush. Re-assemb...
‹
›