Saturday, July 1, 2017

Fuselage

›
Rollover Assembly  ( 1  hr ) Built FWD and AFT Rollbar Frame Assemblies per Sect 37-02 Steps 4 & 5, forty four AN470D4-5 rivets later ...
Friday, June 30, 2017

Fuselage

›
Rollover Assembly  ( 3 hrs ) Cont'd deburring edges of Rollover Frames.  Buffed all w/ scotchbrite, cleaned w/ acetone, then primed w/...
Thursday, June 29, 2017

Fuselage

›
Rollover Structure  ( 4 hrs ) Rotated Fuse back to upright position with Nancy's help.   Per Sect 36-13 confirmed Control Base full Fo...
Wednesday, June 28, 2017

Fuselage

›
Aft Pushrod, Wiring Channel, Cable Links to Rudder, Bearing Bracket Stops ( 3 hrs ) Wrapping up several steps from various sections that a...
Tuesday, June 27, 2017

Fuselage

›
Control Sticks Aligned & Brake Lines Leak Tested ( 2 hrs ) Aligned Control Sticks to be parallel w/in 1/8" top to bottom (vs slig...
Monday, June 26, 2017

Fuselage

›
Control Stick Bases ( 2 hrs ) Primed, then finish painted 4 Rudder Cable Links and the Wiring Channel Ass'ly (goes under dash in cente...
Friday, June 23, 2017

Fuselage

›
Brake Lines ( 3 hrs ) Installed Brake Lines - Crossover and Main Brake Lines per Sect 33-08 & -09/.  Prepped Cable Links for priming p...
‹
›
Home
View web version

About Me

My photo
Steevo
Wickenburg, Arizona, United States
I'm building an RV-14A kit airplane purchased from Van's Aircraft. This website documents construction to show I've built in accordance with FAA's 51% rule. When finished it will be inspected by the FAA or designated representatives, and a special airworthiness certificate will be issued under the Experimental category.
View my complete profile
Powered by Blogger.