Tuesday, November 20, 2018
Avionics
›
Ignition Wiring ( 3 hrs ) Received re-done Floormats and Baggage Floor from Abby at Flightline Interiors. Much improved fit -- Yay! [ N...
Monday, November 19, 2018
Avionics
›
CHT sensors LH side ( 2 hrs ) Completed LH side CHT sensors for cyl 2 & 4. Torqued all four to 28 in-lbs per Alcor Tempest instructi...
Saturday, November 17, 2018
Avionics
›
CHT sensors installed ( 2 hrs ) Installed CHT sensors ( Garmin part # 494-70000-00, Type K, bayonet) in cylinders 1 & 3 on right side....
Thursday, November 15, 2018
Avionics
›
Ignition Wire Routing ( 2 hrs ) Routed ignition wires from Mag and PMag to plugs, along with thermocouple wires for CHT and EGT sensors. ...
Wednesday, November 14, 2018
Avionics
›
Complete installation P909, ANL Fuse Limiter, Shunt & P912 ( 2 hrs ) Torqued terminal bolts and applied torq seal. Added cushion clam...
Tuesday, November 13, 2018
Avionics
›
Shunt and ANL Fuse Limiter ( 4 hrs ) Mocked up installation design of ANL Fuse Limiter Block w/ 60 amp Fuse and Shunt for mounting inside...
Saturday, November 10, 2018
Avionics
›
Mags wired to Ignition Switch & P909 Alternator Power Wire ( 3 hrs) Attached Right, Left and Gnd wires for Mag and PMAG to Ignition Sw...
‹
›