I've started my adventure to build a Van's Aircraft RV14a. For several years, I've been planning to build an Experimental (homebuilt) airplane - once retired.
But first, I needed to get my Pilot's License. (Kinda key !) So... first things first: I retired March 2014 from Caterpillar - and started flying lessons in the Summer of 2014. Soloed a day after Christmas, and got my Private July 2015. Shop set up, tools acquisition, and practise kits during Fall launched me into my build starting Dec 31, 2015 !

I've chosen to build the RV14a since it's about 10% larger than Van's prior models - so it fits my 6'4" frame well. Van's is well known for great value & outstanding flying qualities. It's been a no brainer decision for me. A tour of their facilities and demo flight in Oct 2013 clinched the deal. My wife - also a pilot - exclaimed after her demo flight "retire NOW so you can build one of these". The RV14a fits my mission of a good compromise between cross country & aerobatics. Plus...I fit, too.

So far, one month into building, it's been rewarding. Very challenging, but certainly a learning experience. The builder community is terrific - as is Van's tech support. I'm finished with the Vert Stab and Rudder (Jan 2016). So... with a 5 month delivery lead time, I've ordered the Quick Build Wings and Fuselage.

I hope this blog assists other new builders, just like several others have been valuable to me. Plus it will serve to document my build step by step. Please drop me a line via the "contact me" form on lower RH margin.
Update: April 2020 relocated to Wickenburg, Az to escape Illinois winters.

Tuesday, May 14, 2019

Engine

Exhaust and Fuel System ( 2 hrs )

Completed Heating System w/ last DG-12 adel clamp on engine mount tube, attaching DG-32 holding 2" SCAT hose to LH Vent.  Finally...yay!  Repeated 30 psi air pressure leak test of LH Fuel System (I ordered/received AN 6 sized cap for RH side to insure not leaking during test).  Using soap suds, discovered tiny leak between Fuel Pump and Fuel Filter on pipe threads.  Disassembled, re-applied thread sealant - and NO leaks for 1 hr.
2" SCAT hose routed to LH Vent.  Clamps
position hose clear of  potential rub points

Discovered tiny air leak at pipe threads during pressure
 test (center of pic).  Bubble grew over couple minutes. 
Removed inline filter from Fuel Pump, re-applied
 pipe thread...no leak.

Monday, May 13, 2019

Engine

Exhaust ( 3 hrs )

Installed lock washers under Exhaust flange nuts, & torqued to 190 in-lbs per 48-03, Step 7 & 8.  Needed special 1/4" drive, 1/2" flex socket -- only way to fit onto nuts since exhaust pipe clearance is minimal (VAF has posts noting other builders found same solution.  Surprised Vans instructions don't call out this tool requirement)  Added Sniffle Line Assly per 49-18, Steps 1-6.  Required adding Bottom Cowl Support Bracket plus couple more adel clamps.
1/4" drive, 1/2" flex socket barely fits...
to tighten exhaust flange nuts
Added heat shields in 3 locations




bottom view of heater 2" SCAT hose behind
engine toward LH vent
Sniffle Line Assembly installed.  Yellow cap has blue tape to insure I remove prior to 1st  engine start 

Saturday, May 11, 2019

Engine

Heat Muffs, etc ( 3 hrs )

Completed Step 6, Sect 48-05 - 2" Vent Tee.  Limited space to 1st install two Adel clamps to engine mount tubes, then very large Adel Clamps around 2" Vent.  Used safety wire to hold clamps in position.  Overall took a lot of time to get positioned correctly - and lots of various tools!   Glad that's done !
Using tool to hold clamp closed so I can
hold closed w/ safety wire
In the end, I used many tools to get  'er done.






close up showing clamps secured
And overall shot showing 2" SCAT hose routing 

Friday, May 10, 2019

Engine

Heat Muffs ( 3 hrs )

Installed Heat Muff assemblies per Sect 48-04, Steps 1-6.  Added couple of the SCAT 2" hoses per 48-05.
1 of 2 heat muffs added.

Both heat muffs added, & interconnecting SCAT hose installed

hose connected for air intake 

Thursday, May 9, 2019

Shop Set Up


LED lights added in Hangar

My wife helped today install four 4' LED Shop lights in newly rented hangar.  ( Search Amazon "4 Pack LED Shop Light for Garage: 36W, 4Ft, BBounder 3600 Lumens"  Only $60 for all four.)  The airport staff brought a big ladder that worked perfectly. With Nancy's help, the project got done quickly.


Wednesday, May 8, 2019

Engine

Exhaust install continued ( 2 hrs )

Installed Forward Exhaust Hangar assembly per Sect 48-03, Steps 1-6.   Also started working on heater install, with 2" SCAT hoses, etc.

Hangar from Left rear corner
engine sump to clamp around left
exhaust prior to joining tailpipe.
2" SCAT hose clamped to Right Vent on firewall.

Tuesday, May 7, 2019

Engine

Exhaust installation ( 4 hrs )

Installed Halon fire extinguisher (A344T, 1.25lb 1211 Class B C)  in baggage area  - where pilot can easily reach on wall behind passenger.   Installed LH and RH "Stick to Torque Tube Pushrods" per Sect 41-07, Step 1.  Installed Exhaust per Sect 48-02, Step 4 & 6,7.  Used Permatex #77124, Nickel Anti-Seize Lubricant on slip joints.  Attached Engine Dryer to insure engine interior remains low humidity since opened to install exhaust.  With both 'spark plug' desiccants and circulating dry air, believe I have protection against corrosion.
Halon fire extinguisher in baggage area.
Amerex A344T, 1.25lb 1211 Class B C
LH forward Exhaust added (taped over holes for EGT sensor).  Cover still on rear exhaust port.





From under LH side with rear exhaust added. 
Note: Heat shields in several locations not yet added.
From under tailpipe


Exhaust joining Y for Tailpipe.